Skip to content
csbbmain2

PROJECT

Catholic Schools Broken Bay

Sewer Pump Replacement

CLIENT
Catholic Schools Broken Bay Diocese
SERVICES

Pump Systems, Sewer Service

LOCATION

Lake Munmorah, NSW

TIMELINE
April - June 2024

PROJECT INFORMATION

The Catholic Schools Broken Bay Diocese in Lake Munmorah required a critical upgrade to their sewer pump system. The existing dual sewer pump set was outdated and inefficient, necessitating a complete replacement along with a new power feed to ensure reliable and effective waste management. Our team was tasked with executing this comprehensive project, which involved site preparation, precise excavation, installation of a new dual macerating pump set, and thorough testing and commissioning. The project aimed to enhance the school's waste management system while ensuring minimal disruption to their daily operations.

csbbmain

OBJECTIVES & PRIORITIES

objectives_resource management
Resource
Management
objectives_compliance
Compliance
objectives_quality workmanship
Quality
Workmanship
objectives_minimal disruption
Minimal
Disruption

SCOPE OF WORKS

On-Site Risk Assessment

  • Conducted a thorough risk assessment to ensure safety and compliance with all relevant regulations before commencing work.

Site Preparation and Excavation

  • Set up fencing around the excavation site to secure the area.
  • Located and marked any nearby services along the trench line to avoid damage during digging.
  • Dug a trench 170 meters long, 150mm wide, and 450mm deep from the electrical pit near the sewer pump station to the electrical pit near the admin building.

Conduit and Cabling Installation

  • Laid a 65mm conduit in the trench while simultaneously pulling through a 35mm 4-core 3-phase cable to the pump set.

Pump Removal and Installation

  • Used a vacuum truck to clear out the sewer pit and electrical pit.
  • Disconnected, removed, and disposed of the old pumps and control panel.
  • Supplied and installed a dual macerating pump set in the sewer pit to ensure efficient waste management.

Testing and Commissioning

  • Conducted thorough testing and commissioning of the new pump set to verify proper operation and compliance with standards.

Site Restoration

  • Backfilled the trench and compacted it down to prepare for the re-instatement of grass.
  • Removed fencing from the site and completed general housekeeping to leave the area clean and presentable.
csbb4
csbb3
csbb5
csbb1

RECENT PROJECTS

Let's chat about your next project or ongoing maintenance requirements

Schedule a Meeting